Factory in the Box · Two worked cases · 20 October 2026

Stock up or make locally when deliveries stop?

Three plans face the same daily need. The useful question is how much of that need each plan supplies in time, not how much stock it eventually produces.

A fictional same-product inventory example, not Cost Plus operating data, a drug-production plan or clinical advice. Units are arbitrary supply units, not doses or patients. Costs are not modeled.

The same disruption, three preparations

Every plan starts with 200 usable units. Need is 40 units a day from day 1 through day 30: 1,200 units in all. Outside deliveries normally bring 300 units on days 3, 10, 17 and 24. Deliveries pause on days 8–23, so only days 3 and 24 receive them in this window.

Deliveries only
Use the common starting stock and outside deliveries.
Plus reserve
Add 420 finished units before day 0. This extra lot expires at the start of day 30; unused units then cease to be available.
Plus local
Add local production, not the extra reserve. The setup is ready on day 11, qualified inputs arrive on day 8, a batch takes 2 days and review takes 2 more. Each batch contains 100 units. Required records and a satisfactory review are assumed.

Only the reserve plan gets the extra finished stock; only the local plan gets the local output. The preparations are alternatives, not a combined plan or an equal-budget comparison.

What has happened by day 30?

Default case · need supplied on time
PlanNeed suppliedNeed unmetStock left
Deliveries only78042020
Plus reserve1,200020
Plus local1,14060460

The reserve covers all need in this case. Local production helps, but its first batch is made on day 13 and cannot be released until day 15. Deliveries alone first run short on day 13. Local supply arrives too late to prevent the first 60 units of unmet need.

By day 30, 800 local units have been released. They add 360 units of timely service compared with deliveries alone; the rest increases ending inventory. Producing 800 units is not the same as preventing 800 units of unmet need.

Now let the local inputs arrive late

Keep everything else the same, but move qualified input arrival from day 8 to day 22. Local production must wait. Its first batch is made on day 24 and released on day 26. By day 30 it has released 300 units.

Late-input case · same day-30 window
PlanNeed suppliedNeed unmetStock left
Deliveries only78042020
Plus reserve1,200020
Plus local780420320

Outside deliveries have resumed before that local release. The local plan has more stock left, but supplies no additional need on time in this window. Its earlier missed need remains missed.

The rules behind the comparison

At the start of each day: remove expired stock, receive deliveries and eligible local releases, then serve that day's need. Use the earliest-expiring stock first. Day 0 initializes stock and counts no need.

Base starting stock and outside deliveries each have 30 days of usable life. The reserve has its own expiry day, independent of those lots. Local batches expire 30 days after manufacture, including time held for review.

A missing required record or an unassumed satisfactory review keeps locally made stock held, not available for use. Restoring a record does not itself complete the review. Later arrivals do not backfill need missed on earlier days.

The local input shipment supplies at most ten 100-unit batches. Batches run every 2 days; their review delays may overlap without a review queue. Site readiness here is max(8 days site work, 5 transport, 4 staffing) + 3 qualification = day 11. Packaging and further distribution after release are not timed separately.

The comparison counts timely service, not cost, patients treated, clinical harm or the best real-world manufacturing plan. Buying and rotating the reserve before day 0 are assumed, not simulated. Changing an assumption can change the result.